QUALIFICATIONS
CPC SCIENTIFIC
Rocklin cGMP Facility
Rocklin, CA
PROJECT DESCRIPTION
This project entailed the conversion of an existing two-story office building into a cGMP manufacturing facility. To make the project even more challenging, there were no existing as-built drawings for the building or site. The project team brought Siteline in during schematic design to capture the building—below and above ceiling— the roof, as well as the entire site. Siteline then delivered a point cloud to the architect to help them develop an existing conditions model. This entire site was captured in a single day and the point cloud was processed and delivered to the team two days after the scan was completed.
SIZE:
63,000sf
PROJECT ARCHITECT:
DGA
SERVICES / DELIVERABLES:
Laser Scanning / Point Cloud